Lake Mead intake serving Las Vegas will extend 30 feet deeper
The Southern Nevada Water Authority approved a $20.85 million contract for work planned in 2028, saying it can be done without interrupting service.

At Lake Mead, the deepest intake that supplies the Las Vegas Valley is set to reach 30 feet farther down, to an elevation of 845 feet. The Southern Nevada Water Authority says the extension will help it draw deeper, colder water that is cleaner and easier to treat as the region prepares for possible worsening drought.
The authority’s board approved a $20.85 million contract with California-based Granite Construction Co. on Thursday. The contract covers design, permitting and construction of the intake modification.
The existing third intake has delivered water to the region for more than a decade. It can currently draw water at 875 feet above sea level, 20 feet below the reservoir’s “deadpool” level — a scenario in which water cannot pass through Hoover Dam and downstream deliveries could be disrupted.
How the work will happen
Construction is planned to start in January 2028 and finish that April, water authority spokesman Bronson Mack said. Divers are expected to work at the bottom of the lake for shifts of up to eight hours, removing bolts and welding. The project will use a floating crane and robotic submarines, according to General Manager John Entsminger.
The intake was designed to allow the change, Deputy General Manager of Engineering Doa Ross said. Workers will remove the top two sections rather than alter the concrete structure at the bottom. Ross said extending the intake now was intentionally delayed because placing it lower increases the distance water must be pumped and the resulting expense. The planned elevation is the lowest the structure can go, she said.
Will water service be interrupted?
The authority says customers should not experience a service disruption. Ross said the Las Vegas Valley will fill its reservoirs during the work to protect service. The intake system can provide as much as 900 million gallons per day to the valley, Entsminger said; peak demand during hot summers is 620 million gallons per day.
The authority has not announced a more specific construction schedule beyond the planned four-month window. Ross said the deeper water is the central goal of the project, while Entsminger told the board the agency believes it has the people and technology needed to carry out the work.
This report draws on information from Boulder City Review.